Quick Facts
Location
Commerce, Georgia
Role
Prime Contractor
Completion Date
May 2021
Project Overview
A major utility’s new Banks Crossing Substation was constructed to enhance power supply services and meet the increased needs in Commerce, Georgia.
Project Highlights
16
Drilled Shafts 5’ Dia. x 22’ Deep (Rebar & Anchor Bolt Cages Installed)
4
Direct Embed Poles - 6’ Dia. x 22’ Deep Embedment Holes
Phillips Contribution
Phillips was contracted to install a 4–pole 230kV and 16-pole 115kV dead-end structure consisting of 20 drilled shafts of multiple sizes, 110’ direct–embed poles, and associated hardware. The pre-cast, concrete poles were 110’ long and weighed 60,000 lbs. Phillips developed and enacted a comprehensive work plan to safely erect these direct–embed structures and complete all hardware framing after installation.