Quick Facts
Location
Kingsport, Tennessee
Role
Prime Contractor
Completion Date
February 2019
Project Overview
This project involved the development of the Greenfield site for a new 138kV substation located in Kingsport, Tennessee. Total site disturbance included 5.72 acres and over 54,000 CY of cut to fill.
Phillips Contribution
Phillips performed erosion control installation and maintenance, site grading, storm water installation, and final stabilization. The scope also included drilling, blasting, and crushing of rock to be reused as site fill on a very compact site. Daily site control plans allowed Phillips to complete the work in a safe and timely manner.