Quick Facts
Location
Stanton, Tennessee
Role
Subcontractor
Completion Date
Ongoing
Project Overview
Phillips was subcontracted by Hensel Phelps, Construction Co., for the construction of the South Airport APM Complex Program at Orlando International Airport.
Phillips Contribution
Phillips furnished and installed the site work and Northern Guideway Embankment Surcharge scope of work for the Guideway. The scope of work consisted of constructing mechanically stabilized earth (MSE) walls, embankments, abutments, slab-on-grade, storm drainage systems, underdrain systems, concrete parapet walls, and electrical grounding.
This site work package also included excavating and grading, erosion control measures, and 18” driven precast prestressed piles. A street sweeper was used as often as necessary to remove debris and dirt from the pavement, and a water truck was utilized to maximize dust control.
Phillips was able to contribute to the Small Business Participation with a goal of 20% MWBE, LDB, and DBE.