Project Overview
The BlueOval City campus spans 3,600 acres and will be home to electric vehicle and battery manufacturing operations. This facility will reimagine the design and construction of electric vehicles and batteries. The project is expected to create over 5,800 jobs and is on schedule to begin production by 2025.
Project Highlights
100K
LF Silt Fence
200
AC Heavy Clearing
500K
CY Stripping
11M
CY Excavation
75K
TN Lime Drying & Stabilization
340K
SY Cement Stabilization
6,000
LF Temporary Storm Drainage
1.5M
TN Crushed Stone Base
Phillips Contribution
Phillips is delivering site development packages for this two-phased manufacturing campus through multiple contracts. Scope of work includes erosion control and maintenance, clearing and grubbing, excavation and embankment, demucking, storm drainage systems, subgrade prep, cement stabilization, lime stabilization, building pad roadway and parking lot base construction, and temporary grassing.