Quick Facts
Location
Polk County, Florida
Role
Prime Contractor
Completion Date
September 2014
Project Overview
Phillips was contracted to complete all site work activities associated with the construction of the Project Garden Distribution Center located on an 85-acre site in Lakeland, Florida.
Project Highlights
8,000
LF Silt Fence
310K
CY Excavated
250K
CY Fill Material Imported & Placed
13,000
LF 15-72" Stormwater Drainage Piping Installed
2,000
LF 8" Sanitary Sewer Line
1,500
LF Force Main
1,000
LF Water Main
7,500
LF Fire Main
20,000
LF Curbing
80,000
SY Asphalt Paving
78,000
SY Seeded & Sodded
Phillips Contribution
The scope of work completed by Phillips for the project included installation and maintenance of silt fence; clearing and grubbing of the 85-acre site; excavation of material; import and placement of fill material; installation of storm water drainage piping, 8” sanitary sewer line, force main, water main, and fire main; construction of a lift station and curbing; placement of asphalt paving; and seeding and sodding of the site.
Phillips mobilized to the project site in late September of 2013 following an extremely wet summer in central Florida. As a result, most of the project site was covered with standing water at the time of project mobilization. To ensure the project schedule was maintained, Phillips deployed the necessary equipment and personnel to install erosion control measures, clear the site, and complete earthwork, despite the wet conditions at the site. Completing these work activities under the less-than-desirable conditions allowed Phillips to meet the originally established schedule.